July 30, 2026

Five years changed the energy storage map

Two world maps of operational energy storage projects of 1 MW or more: sparse in 2020, far denser by July 2026 led by China, the US, Europe and Australia, beside a large 2.5x figure for tracked power capacity since 2020.

Global large-scale storage power capacity has grown to two and a half times its 2020 level. Using Aegir Insights' global storage database, we mapped the operational subset by commissioning year, showing three clear trends:

  • Storage is no longer a niche asset class; it has become standard grid infrastructure. Our database has added more than 2,700 newly operational projects in about five years, with tracked power capacity up ~2.5x.
  • Batteries took over: 94% of the projects built since 2020 are Li-ion.
  • The map has changed. The 2020 fleet clustered in Europe, Japan, and parts of the US and China. The build-out since runs through China above all, then Texas, California and Arizona. Australia has accelerated, and new markets such as Saudi Arabia and Chile have emerged.

Battery storage projects by country

By country, the build-out is heavily concentrated. China accounts for a little over half of all the capacity added since 2020, and China and the United States together for roughly three quarters of it. Australia, the United Kingdom and India follow. Germany added more individual projects than any other European market, but at an average size well under 10 MW, against nearly 50 MW in the United Kingdom. Storage has also arrived in markets that barely registered in 2020: Saudi Arabia, Chile, Bulgaria and Ukraine all now have grid-scale fleets. In total, 82 countries have brought at least one project of 1 MW or more online since 2020.

#MarketCapacity added (GW)Projects addedShareAvg size (MW)
1China115.376253%151
2United States47.678122%61
3Australia10.1535%190
4United Kingdom6.91473%47
5India4.7112%423
6Saudi Arabia3.061%500
7Germany2.63521%7
8Chile2.4191%128
9Ukraine1.651%330
10Canada1.4301%47

The ten markets with the most capacity added. Operational grid-connected storage of 1 MW or more, commissioned 2021 to July 2026. Source: Aegir Insights global storage database.

The next 2,700 projects will arrive faster than the last. Want a view of the pipeline? Aegir Insights tracks ~10,000 grid-scale storage projects across 120+ markets worldwide, from operational fleet to development pipeline, each carrying modeled project economics. Reach out for a walk-through.