Offshore wind cable manufacturers: 57 GW still open

Bar chart: Offshore wind capacity in development outside China with no array or export cable order on record, by expected COD year, rising from 0.2 GW in 2028 to 27.7 GW in 2032, against Aegir’s Central forecast. Source: Aegir Insights, November 2026.

57 GW of offshore wind projects due online by 2032 haven’t picked a cable supplier yet. So far, wind farm cables are a concentrated market: Four cable makers hold two in three array and export cable orders between them.

  • Four suppliers lead the order book: Prysmian (59 orders), Nexans (41), NKT (39) and Hellenic Cables (30) hold 169 of the 256 array and export cable orders we track. Including interconnectors, the same four hold 274 of 371.
  • Array and export cables have different leaders: In array cables, JDR Cable (25 orders) is close behind Prysmian (28), followed by Hellenic Cables, Nexans and TKF. Export cables are led by NKT (36), Prysmian (31), Nexans and LS Cable (26 each).
  • 57 GW is still open: 90 offshore wind projects outside China with an expected COD in 2028–2032 have no array or export cable order on record yet.
  • Not all of it will be built: Our Central forecast has 52 GW of offshore wind coming online outside China in 2028–2032, and around 22 GW of that already has a cable supplier. That leaves room for roughly 30 GW of the open pipeline in this period.
  • The UK leads the open pipeline: Around 19 GW, ahead of Germany and South Korea. Most of the UK’s open capacity is due online in 2031 and 2032.

With the Aegir Cable Order Book, suppliers and developers can track every award by cable segment and screen the projects still to contract by market and COD year.

For how supplier concentration rises with voltage class, see our earlier reading of the offshore cable order book.

Reach out for a walk-through: www.aegirinsights.com/contact